...shall be liable to the Government for liquidated damages in the amount set forth in Provision No. C.28 as fixed, agreed and liquidated damages for each calendar day of delay or fraction thereof until such time as it accepts delivery of the petroleum, or until the contract... | |
| United States. Congress. House. Committee on Appropriations - 1952 - 1076 halaman
...or impossible to ascertain the actual damages for the delay and in lieu thereof the Contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day of delay until the delayed work is complete or accepted, the amount as set forth in the specifications or in Article 1.... | |
| 1955 - 1520 halaman
...Government for the delay will be Impossible to determine, and therefore in lieu thereof the Contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day of delay the amount set forth In the Bailment Agreement loaning such aircraft and designated as "Liquidated... | |
| United States. Congress. Senate. Committee on Interior and Insular Affairs - 1959 - 86 halaman
...the Contracting Officer, in the amount set forth in the specifications or accompanying papers, for fixed, agreed, and liquidated damages for each calendar...of delay until the work is completed or accepted, or if liquidated damages are not so fixed, any actual damages occasioned by such delay. (6) The right... | |
| United States. Congress. Senate. Committee on the Judiciary - 1959 - 1296 halaman
...Government for the delay will be impossible to determine, and therefore in lieu thereof the Contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day of delay the amount set forth elsewhere in this contract; Provided, That the Government may terminate this contract... | |
| 1960 - 692 halaman
...liable to the Government, in the amount set forth In the specifications or accompanying papers, for fixed, agreed and liquidated damages for each calendar...of delay until the work is completed or accepted, or if liquidated damages are not so fixed, any actual damages occasioned by such delay. (c) The right... | |
| United States. Congress. House. Appropriations - 1961 - 336 halaman
...liable to the Government, in the amount set forth in the specifications or accompanying papers, for fixed, agreed and liquidated damages for each calendar...of delay until the work is completed or accepted, Or if liquidated damages are not so fixed, any actual damages occasioned by such delay. (c) The right... | |
| 1961 - 576 halaman
...liable to the Government, in the amount set forth in the specifications or accompanying papers, for fixed, agreed and liquidated damages for each calendar...of delay until the work is completed or accepted, or if liquidated damages are not so fixed, any actual damages occasioned by such delay. (c) The right... | |
| |