| 1979 - 1186 halaman
...beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such...the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or service to be furnished by the subcontractor were... | |
| 1972 - 684 halaman
...beyond the control and without the fault or négligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such...negligence of either of them, the Contractor shall not be liabto for any excess coats for failure to perform, unless the supplies or services to be furnished... | |
| 1972 - 862 halaman
...beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such...negligence of either of them, the Contractor shall not be Uabte for any excess costs for failure to perform, unless the supplies or services to be furnished... | |
| 1969 - 628 halaman
...the fault or negligence of the Contractor. If the failure to perform is caused by the default of а subcontractor, and if such default arises out of causes...the Contractor shall not be liable for any excess costs for failure to )>erforin. unless the supplies or services to be furnished by the subcontractor... | |
| 1973 - 968 halaman
...beyond the control and without the fault or negligence of the Contractor. If the failure to perform Is caused by the default of a subcontractor, and If such...fault or negligence of either of them, the Contractor •hall not be liable for any excess costs for (allure to perform, unless the supplies or services... | |
| 1964 - 1202 halaman
...beyond the control and without the fault or negligence of the Contractor. If the failure to perform Is caused by the default of a subcontractor, and if such...subcontractor, and without the fault or negligence of either of 1 When Standard Form 19 Is used, the words "the clause of this contract entitled 'Disputes' " shall... | |
| 1964 - 432 halaman
...beyond the control and without the fault or negligence of the Contractor. If the failure to perform Is caused by the default of a subcontractor, and If such...subcontractor, and without the fault or negligence of either of 1 When Standard Form 19 is used, the words "the clause of this contract entitled 'Disputes' " shall... | |
| 2001 - 770 halaman
...strikes, freight embargoes, and unusually severe weather. (c) If the Contractor's failure to perform is caused by the default of a subcontractor, and if such...subcontractor, and without the fault or negligence of either, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies... | |
| 1969 - 790 halaman
...subcontractors, the Contractor shall not be liable for any excess costs If the failure to perform the contract arises out of causes beyond the control of both the...the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or services to be furnished by the subcontractor... | |
| 1967 - 694 halaman
...subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control of both the...the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or services to be furnished by the subcontractor... | |
| |