... Completion . Whether the contract has been completed on either side . is what is called a mixed question of law and fact . What any agreement means is a question of law ( for the judge ) ; what are the facts as to satis- fying that ...
... Completion . Whether the contract has been completed on either side . is what is called a mixed question of law and fact . What any agreement means is a question of law ( for the judge ) ; what are the facts as to satis- fying that ...
Halaman 10-13
... completion , it must be filled up strictly in accordance with the authority given and within a reasonable time . But if any such instrument , after completion , is nego- tiated to a holder in due course , it is valid and effectual for ...
... completion , it must be filled up strictly in accordance with the authority given and within a reasonable time . But if any such instrument , after completion , is nego- tiated to a holder in due course , it is valid and effectual for ...
Halaman 14-3
... completion of the work , except as provided in the Contract . The Board reserves the right to reject any or all bids or to accept any bid , should it deem it for the interests of the City so to do . The work is to commence within ten ...
... completion of the work , except as provided in the Contract . The Board reserves the right to reject any or all bids or to accept any bid , should it deem it for the interests of the City so to do . The work is to commence within ten ...
Halaman 14-5
... completion of the work in full conformity with the specifications . The prices bid must be stated both in words and in figures . All bids which do not contain prices for all the items which are called for in the forms for bids , or ...
... completion of the work in full conformity with the specifications . The prices bid must be stated both in words and in figures . All bids which do not contain prices for all the items which are called for in the forms for bids , or ...
Halaman 14-9
... until its completion , on or before Opinions will readily differ as to the amount of red tape desirable in connection with any delay . Another form reads : 1. The Contractor shall begin " INFORMATION FOR BIDDERS 14-9.
... until its completion , on or before Opinions will readily differ as to the amount of red tape desirable in connection with any delay . Another form reads : 1. The Contractor shall begin " INFORMATION FOR BIDDERS 14-9.
Edisi yang lain - Lihat semua
Istilah dan frasa umum
acceptance action agent agreed agreement amount arbitration Architect Article authority award bank bidder bill bill of exchange Board Bond buyer carrier certified check chapter Chief Engineer City claim clause Commission common carrier Common Law Company completion construction Contract Form Contracting Officer Contractor contributory negligence corporation cost court of Equity damages deed delay delivery deposit determine drawee drawer duty easement eminent domain employee estimate evidence executed fact Franktown fraud furnish hereby holder indorsement injury interest Item jury labor land lawyer liable liquidated damages materials matter ment municipal necessary negligence negotiable instrument notice otherwise Owner paid party payable payment performance person presented proper Proposal quitclaim deed railroad reasonable remedy seal Section secure seller signature sometimes specifications statute Statute of Frauds sub-contractor sufficient surety thereof tion torts ultra vires unless warranty writing
Bagian yang populer
Halaman 10-12 - An instrument is payable on demand — 1. Where it is expressed to be payable on demand, or at sight, or on presentation; or 2. In which no time for payment is expressed. Where an instrument is issued, accepted, or indorsed when overdue, it is, as regards the person so issuing, accepting, or indorsing it, payable on demand.
Halaman 10-7 - Act. In any case not provided for in this act, the rules of law and equity, including the law merchant...
Halaman 10-32 - Where a foreign bill appearing on its face to be such is dishonored by non-acceptance, it must be duly protested for nonacceptance, and where such a bill which has not previously been dishonored by non-acceptance is dishonored by non-payment, it must be duly protested for non-payment. If it is not so protested, the drawer and indorsers are discharged. Where a bill does not appear on its face to be a foreign bill, protest thereof in case of dishonor is unnecessary.
Halaman 10-25 - As respects one another, indorsers are liable prima facie in the order in which they indorse; but evidence is admissible to show that as between or among themselves they have agreed otherwise. Joint payees or joint indorsees who indorse are deemed to indorse jointly and severally.
Halaman 10-15 - The acceptance of a bill is the signification by the drawee of his assent to the order of the drawer. The acceptance must be in writing and signed by the drawee. It must not express that the drawee will perform his promise by any other means than the payment of money.
Halaman 10-20 - Where an indorsement is conditional, a party required to pay the instrument may disregard the condition, and make payment to the indorsee or his transferee, whether the condition has been fulfilled or not. But any person to whom an instrument so indorsed is negotiated, will hold the same, or the proceeds thereof, subject to the rights of the person indorsing conditionally.
Halaman 10-29 - Notice of dishonor is not required to be given to an indorser in either of the following cases — 1. Where the drawee is a fictitious person or a person not. having capacity to contract, and the indorser was aware of the fact at the time he indorsed the instrument; 2. Where the indorser is the person to whom the instrument is presented for payment; 3. Where the instrument was made or accepted for his accommodation.
Halaman 10-15 - Where the instrument contains or a person adds to his signature words indicating that he signs for or on behalf of a principal, or in a representative capacity, he is not liable on the instrument if he was duly authorized; but the mere addition of words describing him as an agent, or as filling a representative character, without disclosing his principal, does not exempt him from personal liability.
Halaman 15 - ... unless the agreement, upon which such action shall be brought or some memorandum or note thereof, shall be in writing, and signed by the party to be charged therewith, or some other person thereunto by him lawfully authorized.